Flag a Deadline Risk Before It Is Missed
You → the person authorized to decide the internal delivery date
An internal demonstration handout is due Friday. A confirmed request has added an illustrations page. You have finished the text, but the illustrations page and its layout check remain. Having checked that remaining work against your available time, you no longer consider Friday a reliable estimate. Monday is your current estimate if the illustrations are available and the requested scope stays fixed; neither condition is fully confirmed. No safety-critical delivery, contractual dispute or formal performance process is involved.
Before you use this
Use this when
Report the verified change and ask the responsible person to consider one date adjustment before the original deadline. Your estimate does not change a shared commitment or erase work obligations.
Stop if
Contractual consequences, safety, formal performance disputes or pressure to misstate progress require the relevant responsible process, not optimistic wording or a unilateral new date.
Your first line
Recommended first line
Use only progress and estimates you can support. State the assumptions rather than predicting a recovery you cannot verify. You are asking for a date change, not announcing one or promising the manager a particular impression of you. Scope cuts, extra staff or a colleague taking over would also need their own authorized decisions and actual acceptance; do not volunteer them.
The added illustrations page puts Friday's handout at risk. The text is done; the page and layout check remain. Monday is my estimate if the illustrations arrive and scope stays fixed. Could you approve that date change?
These are examples, not every possible response. If none fits, nothing has happened yet, or you're unsure, leave the response unselected or use Clear response. This does not confirm that the scenario applies; follow the scope and stop conditions above.
Clears this scenario's response. Your goal stays the same.
What you can observe
What happened next?
For: Report the risk and request one adjustment